CF Electrical Services Living Report · Landmark Arms cfelectrical.ca
Prepared for The Owners, Strata Plan VR 165 · Electrical Planning Report + EV Ready Plan · Projects 2026-VR165EPR · 2026-VR165EVRP

Living Report · Electrical Planning Report

At its busiest hour of the year, this building uses less than a third of its electrical service.

Landmark Arms is heated by natural gas, and so is its hot water — so the electrical service does very little work today: about 1.2 kW per suite at peak. That leaves real room for EV charging and an electric hot water conversion together, with a little to spare. This page carries both of your documents: the Electrical Planning Report, and the EV Ready Plan that turns its charging scenario into a concrete design.

Spare at the main service
0%
of the 400 A main service, unused at the year's busiest hour
ELEC. MECH. PARKADE · 26 STALLS 3 STOREYS · 26 SUITES · UNDERGROUND PARKADE · BUILT 1974 · GAS HEAT & HOT WATER ILLUSTRATIVE
0
Residential suites
0
Parkade stalls · one per suite
0 A
Main service · 120/240 V
0 kW
Peak demand per suite
0
Year built · original equipment

01 · Capacity, measured

How much electrical room is left.

Capacity is assessed at the strata's own main fuse using a full year of BC Hydro data — the building's genuine busiest hour, plus the 25% safety factor Technical Safety BC requires.

Main service — 400 A fused switch
0kW spare
68.1% free Comfortable spare
30.6 kW design peak of 96.0 kW capacity · 400 A × 240 V
The whole property — all 26 suites and the house loads — at its design peak, assessed at the Siemens fusible switch in the parkade electrical room.
House distribution — 200 A disconnect
0kW spare
70.2% free Comfortable spare
14.3 kW design peak of 48.0 kW capacity · 200 A × 240 V
The common loads: laundry, pumps, building lighting, fire alarm. Fed from the same 400 A service, so its demand is already counted inside the service peak — the two figures aren't added together.
The busiest hour of the year was August 25, 2025 at 8:00 PM — a summer evening, drawing 24.464 kWh across all 27 metered points. With the 1.25× safety factor required by TSBC IB-EL 2023-01 Rev. 2, that gives the 30.6 kW design peak — about 1.2 kW per suite. The reason it's so low: space heating and hot water are both natural gas, so the electric range is the only major load in a suite. The spare is large because the service is doing very little work today, not because it was generously sized.

02 · Where the power flows

From the street to your suite, in one diagram.

Tap any box to see what it is, what it powers, and where the spare capacity sits.

Selected

    03 · What draws power today

    Heat and hot water are gas — the range is the big electric load.

    Two gas boilers heat the suites through hydronic baseboards, and a third gas boiler heats the domestic hot water. Neither appears on the electrical service. Here is what does.

    A note on the numbers: these are the loads identified at the site visit — not a breakdown of the 30.6 kW measured peak. The common-property load is a substantial share of this building's total demand, because the house panel feeds the shared laundry, the pumps and the building lighting.

    04 · The future, scenario by scenario

    What could go electric — and does it fit?

    Select a scenario to see the report's estimated load, its verdict, and what it does to the spare capacity. The scenarios are modelled separately, as the Regulation requires — and they draw on the same spare.

    In use today Added load Spare Over capacity

    The one-sentence version

    The spare supports EV charging through an energy management system, together with converting the gas hot water to electric, with a little capacity still in reserve. It does not support fitting heat pumps in all 26 suites — that would be a larger project involving a new BC Hydro service and likely a renovation of the main electrical room.

    05 · Equipment health

    Original to 1974, in good condition — with two practical notes.

    The main fused switch, meter centre, house panel and suite panels are in good condition, and the service has ample spare for the loads assessed. No upgrades or modifications to increase capacity are required or recommended. The notes worth knowing: the electrical room is tight, and some suites still carry the original fuse panels.

    06 · Our recommendations

    What to do, in plain order.

    Part two · EV Ready Plan · BC Hydro CS-4042

    Every stall, EV Ready — with no service upgrade.

    "EV Ready" does not mean chargers get installed. It means the infrastructure is in place so every resident can easily add a charger when they're ready — an energized, networked, managed circuit at every residential stall from day one. This plan is built to BC Hydro's program standard, which is also what makes the building eligible for BC Hydro's EV rebates.

    0
    EV Ready stalls · one per unit
    0
    Managed circuits · 4 stalls each
    0 kW
    Software-held charging cap
    0 kW
    Spare left after full build
    $0
    Service upgrade required

    07 · The recommended solution

    A new EV panel, its own meter, and seven smart circuits.

    Chargers are fed from a new 250 A EV panel on a new BC Hydro meter — so EV electricity never touches the strata's common-area account, and the existing house capacity is untouched. Because the electrical room is tight, the panel goes in the adjacent mechanical room.

    New 250 A EV panel

    Mechanical room · new BC Hydro meter
    Connected to the main service and metered separately at the utility level. Its 60.0 kW capacity holds the 49.9 kW managed peak with margin for future chargers.

    Seven managed circuits

    2-pole 40 A · #8 AWG copper
    Each circuit serves up to four chargers through a 4:1 load-sharing strategy — seven breakers instead of twenty-six, and the breaker is never overloaded.

    The charger

    Fractal EV FR48C · set to 32 A · 7.68 kW
    A networked Level 2 unit with an on-unit display, rated to 48 A and commissioned at 32 A for the shared build. Equivalent BC Hydro–eligible products may be substituted.

    Management & billing

    Foresta Energy · pay-per-use
    Software coordinates all 26 chargers within the 49.9 kW cap and bills each resident per session. Residents without EVs pay nothing toward the system, and the strata can set a slight premium on the BC Hydro rate to contribute to the contingency.

    Parkade network

    4 wireless access points · $8,000
    The parkade has no wireless coverage today. The plan includes a new network linked to internet service in the electrical room — one access point per 50 ft of cabling run, confirmed at detailed design.

    Chargers arrive with the cars

    No waiting on electrical work
    Every stall is EV Ready from day one. A charger is added at a stall when the owner acquires an electric vehicle; registering on the billing platform brings it into the load pool with no further electrical work.

    08 · How the sharing works

    One breaker, four stalls — and nobody waits for a charge.

    One 40 A breaker feeds a circuit shared between four stalls. The energy management system dynamically allocates power to whichever chargers are operating — when a car unplugs, current is instantly reallocated to the rest. Tap a scenario:

    5 kWh
    a typical day's driving (25 km, the BC Hydro planning minimum) — 39 minutes at full rate, 2.6 hours even at the fully shared rate
    ~3×
    the overnight window delivers about 77 km of range even with every charger sharing — roughly three times the 25 km/day target. Every vehicle meets the BC Hydro minimum under all operating conditions
    14/26
    residents answered the driving survey (53.8%). Most who drive travel under 20 km a day; one already drives an EV and four expect one within one to five years. The survey supports the planning basis rather than overriding it

    09 · Cost & rebates

    What it costs, and what BC Hydro pays back.

    The infrastructure is the strata's one-time build. Chargers are a separate per-stall cost, paid as owners acquire electric vehicles. Pricing is before tax and valid for 30 days from the plan date; final pricing is confirmed by the installing contractor at detailed design.

    The strata's build · once
    EV Ready infrastructure — seven circuits at $8,500, permit $4,000, engineering design $7,150$70,650
    Telecom & parkade wireless network — four access points$8,000
    Total infrastructure, before tax$78,650
    BC Hydro EV Ready infrastructure rebate — $600 × 26 stalls−$15,600
    Net infrastructure after rebate, before tax$63,050
    Per charger · as owners buy EVs
    Fractal FR48C charger + installation$1,500 + $500
    BC Hydro charger rebate, claimed as each is installed−$1,000
    Net per charger$1,000
    Rebates need pre-approval before purchase and installation. The strata already holds BC Hydro pre-approval SC-027452 for this plan; the installation rebates are a separate application, and BC Hydro confirms it can supply the load before the strata commits the cost. Ongoing software is an operating cost as chargers come online — $180 per charger per year plus a 10% transaction fee, or 7¢ per kWh — with the electricity itself billed to the residents who use it.

    10 · Alternatives considered

    Two other designs were on the table.

    The recommended 4:1 build delivers full BC Hydro charging performance at the lowest installed cost while keeping spare capacity for future growth. Here is what else was considered, and why.

    A REASONABLE FIRST STEP

    One or two shared chargers, ~$10,000

    Fed from the four spare positions on the existing house panel, at the visitor stall or the parkade wall — no new panel, no new meter, no load management, and the house capacity easily carries it (two chargers draw 15.4 kW against 33.7 kW of house spare). Why not selected: it doesn't make the property EV Ready or access the infrastructure rebate on the same basis, mixes EV use into the strata's common meter, and uses every spare position on the house panel. It remains a reasonable near-term step if council wants charging available quickly without committing to the full build.

    RULED OUT

    Dedicated 1:1 circuits, no sharing

    A dedicated 40 A circuit to every stall, full 7.68 kW to every vehicle at all times. Why not selected: it needs 26 breakers instead of seven, far more conductor and conduit, and its 199.7 kW unmanaged load is more than three times the 65.4 kW of measured spare — forcing a service upgrade. The 4:1 solution already meets BC Hydro's charging performance requirement in full, so the extra cost buys no real benefit at typical residential charging patterns.

    Before any work proceeds

    This is a plan, not a permit package. Detailed design and permit drawings follow under a separate engagement once the strata accepts the plan (the engineering design fee above covers that work). Common-property charging infrastructure needs a strata council resolution — and where the work affects common property in a way that requires owner approval, a 3/4 vote — and the strata notifies BC Hydro of the load addition before energizing.

    11 · Methodology & the fine print

    For those who want to check the math.